依據"Release Team Meeting results (the Juelich Edition)":
Now on to the draft of the timeline:
August 2007Of course, "Early September" is only an internal goal as of now, the
Start of the first BSP marathon for Lenny, lasting till November. [1]
Early September 2007
The list of release blockers for Lenny is frozen.
Early March 2008
Very soft freeze: Please be extra careful with new versions, and new
transitions. At this point, the list of release goals is frozen.
Start of the second BSP marathon for Lenny.
Early April 2008
Freze of the essential toolchain.
Mid of June 2008
Freeze of the non-essential toolchain and all libraries.
Mid of July 2008
Full freeze.
Early September 2008
Release!
official communications is "in the second half of 2008".
[1] http://wiki.debian.org/BSPMarathonLenny